East Milton-Lower Mills pipeline contract award expected this month

from The Dorchester Reporter

The Massachusetts Water Resources Authority is expected to award a bid for a water pipe replacement and rehabilitation project spanning from Milton to Lower Mills at its Dec. 16 board meeting.

The cost of the project, which will include the replacement of 9,200 feet of water pipe from East Milton Square to Lower Mills, has been put at about $20 million with a 3-1/2-year completion schedule, said MWRA spokeswoman Ria Convery. Depending on the weather, work could begin as early as February, she said. (Read the full story here.)